Principal Employer
The Executive Engineer, Ujjani Canal Division No. 8, Solapur.
Scope of Work
Closed Pipe distribution system work of entire scheme, formation of WUA’s, Training farmers, running & maintenance of complete PDN system with co-operation of farmers for five years & handing over the PDN system to WUA’s of farmers, Obtaining Environmental clearance of scheme etc.
Construction of Pump House Stage-I & II & Allied Civil, Mechanical and Electrical work, Rising Main 1, 2A, 2B, Delivery Chamber-1 & 2, Gravity Main 1, 2, 3 & 4, Closed Pipe Distribution System work of the entire scheme, for Lakadi Nimbodi Lift Irrigation Scheme, Tal. Indapur, Dist. Pune.