NH-544G · PACKAGE 3← Back To Projects

NH-544G / PACKAGE 3

Physical Progress — April 2025

Physical Progress — April 2025

Package 3 | Monthly progress report — April 2025.

Scroll the table horizontally to view all columns on smaller screens.

Sr. NoDescriptionQtyUnit
Earth Work Bill No-02
1Clearing and grubbing for road land complete as per Technical Specification Clause 201170.37Hect
2Roadway excavation necessary for construction of roadway and drainage includes dressing, trimming and compacting the cut formation in accordance with requirements of lines, grades and cross fall complete as per Technical Specification section 301 and disposal of all cut material including necessary stacking of suitable material with all lifts and leads.
a)All types of Soils9,95,588Cum
d)d) Excavation for roadway in hard rock requiring controlled blasting by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections, loading and disposal of all cut material including necessary stacking of suitable material with all lifts and leads complete as per Technical Specification Section 301 & 3023,94,413Cum
3Construction of embankment complete as per technical specification clause 305 with all leads and lifts.
b)Embankment with suitable materials deposited at site from roadway and drainage excavationCum
From roadway excavation7,47,909Cum
From Borrow Area21,81,803Cum
4Construction of subgrade complete as per drawing and technical specification clause 305 with all leads and lifts.
a)Subgrade with approved material obtained from approved borrow areas2,49,386Cum
Providing and Construction of Granular Sub-base (Grade VI) by Mix in Place method, complete as per drawing and Technical Specifications Clause 401.69,423Cum
5Providing and Construction of CTB with approved material complete as per MORTH Technical Specification Clause No. 406 (WMM)39,634Cum
Providing and Construction of CTB with approved material complete as per MORTH Technical Specification Clause No. 406 (WMM)14,157Cum
PAVING COURSES
Providing and laying Prime coat over granular surface as per drawing and technical specifications.1,86,030SQM
Providing and applying bituminous Tack coat @ 2.0 to 3.0 kg /10 sqm over prepared bituminous surface with bituminous emulsion all complete as per Technical Specification Clause 5031,86,030SQM
Providing and laying Dense Bituminous Macadam (DBM with VG-40, grading-2) course complete as per MoRTH Technical Specification Clause Nos 501 & 505.10.972Cum
CULVERTS
6Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads.Cum
a) In all types of Soils by mechanical means18,865Cum
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M151,397.0Cum
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M3011,876Cum
Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 16001,505MT
Providing and Laying Reinforced cement concrete for Box / Slab culverts in Superstructure excluding cost of steel complete as per drawing and Technical Specifications Sections 1500, 1700 and 2300.
a)RCC Grade M 304,449Cum
BRIDGES
7Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads.Cum
a)In all types of Soils by mechanical means34,659Cum
a)Providing and laying Cement Concrete in foundation including centring and shuttering etc. as per Drawings and Technical Specifications Section 1500,1700 and 2100 (Excluding cost of steel)1,840Cum
Providing and laying Cement Concrete in foundation including centring and shuttering etc. as per Drawings and Technical Specifications Section 1500,1700 and 2100 (Excluding cost of steel)
a) M307,516cum
b) M353,286cum
Providing and laying Cement Concrete in sub-structure including centring and shuttering etc. as per Drawings and Technical Specifications Section 1500,1700 and 2200 (Excluding cost of steel)
b) RCC M302,533cum
c) RCC M352,564cum
Providing and laying Reinforced Cement Concrete in Super structure complete as per Drawings and Technical Specifications Section 1700 & 2300.(Excluding cost of steel).
a) RCC M30864cum
b) RCC M354,084cum
d) RCC M40620cum
d) RCC M451,573cum
Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 16001,980MT
Underpasses
8Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads.
a) In all types of Soils by mechanical means24,733Cum
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M151,246Cum
b)Providing and laying Cement Concrete in foundation including centring and shuttering etc. as per Drawings and Technical Specifications Section 1500,1700 and 2100 (Excluding cost of steel)
a)RCC M302,553cum
b)RCC M351,577cum
Providing and laying Cement Concrete in sub-structure including centring and shuttering etc. as per Drawings and Technical Specifications Section 1500,1700 and 2200 (Excluding cost of steel)
b) RCC M301,514cum
c) RCC M351,821cum
Providing and laying Reinforced Cement Concrete in Super structure complete as per Drawings and Technical Specifications Section 1700 & 2300.(Excluding cost of steel).
a) RCC M301,030cum
b) RCC M35986cum
b) RCC M40286cum
d) RCC M45, Cast in situ1,605cum
Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 16001,269MT
Other Work
10Providing and construction of Toe wall complete as per the drawings and Technical Specifications 1500, 1600,1700, 2100 & 2200 as directed by the Engineer.
a) Excavation in all types of soil38,700Cum
b) PCC M 15 using batching plant1,350Cum
c) RCC Grade M 30 for foundation9,742Cum
e) Reinforcement945MT
11Re Panel Erection4,214SQM
12RE wall Panel Casting15,086SQM
13Boundry wall Panel Erection2,110RMT
14Road side drains (Shoulder drain,Linne drain,Unline Drain)8,954RMT

Back to Package 3

Building the Nation, Beaming with pride

Registered Office

Amar Business Zone, C-Wing, Level 13, Baner,
Pune 411045, India

Building the Nation, Beaming with pride

Registered Office

Amar Business Zone, C-Wing, Level 13, Baner,
Pune 411045, India

© 2026 Rajpath Infracon Pvt. Ltd. All rights reserved.

CRISIL A-/Stable · Guinness World Record Holders

Building the Nation, Beaming with pride

Registered Office

Amar Business Zone, C-Wing, Level 13, Baner,
Pune 411045, India

Building the Nation, Beaming with pride

Registered Office

Amar Business Zone, C-Wing, Level 13, Baner,
Pune 411045, India

© 2026 Rajpath Infracon Pvt. Ltd. All rights reserved.

CRISIL A-/Stable · Guinness World Record Holders