NH-544G · PACKAGE 3← Back To Projects
NH-544G / PACKAGE 3
Original project schedule: milestone dates, days from the appointed date, and planned progress.
Scroll the table horizontally to view all columns on smaller screens.
| Date | Milestone | Days from appointed date | Planned progress |
|---|---|---|---|
| 29.08.2024 | Project Milestone-I | 180 | 20% |
| 02.03.2025 | Project Milestone-II | 365 | 35% |
| 18.09.2025 | Project Milestone-III | 565 | 75% |
| 01.03.2026 | Schedule Completion Date | 730 | 100% |