NH-544G · PACKAGE 3← Back To Projects

NH-544G / PACKAGE 3

Physical Progress — March 2025

Physical Progress — March 2025

Package 3 | Monthly progress report — March 2025.

Scroll the table horizontally to view all columns on smaller screens.

Sr. NoDescriptionQtyUnit
Earth Work Bill No-02
1Clearing and grubbing for road land complete as per Technical Specification Clause 201170.37Hect
2Roadway excavation necessary for construction of roadway and drainage includes dressing, trimming and compacting the cut formation in accordance with requirements of lines, grades and cross fall complete as per Technical Specification section 301 and disposal of all cut material including necessary stacking of suitable material with all lifts and leads.
a)All types of Soils9,10,968Cum
d)d) Excavation for roadway in hard rock requiring controlled blasting by drilling, blasting and breaking, trimming of bottom and side slopes in accordance with requirements of lines, grades and cross sections, loading and disposal of all cut material including necessary stacking of suitable material with all lifts and leads complete as per Technical Specification Section 301 & 3023,61,323Cum
3Construction of embankment complete as per technical specification clause 305 with all leads and lifts.
b)Embankment with suitable materials deposited at site from roadway and drainage excavationCum
From roadway excavation7,9,109Cum
From Borrow Area21,91,355Cum
4Construction of subgrade complete as per drawing and technical specification clause 305 with all leads and lifts.
a)Subgrade with approved material obtained from approved borrow areas2,21,887Cum
Providing and Construction of Granular Sub-base (Grade VI) by Mix in Place method, complete as per drawing and Technical Specifications Clause 401.61,735Cum
5Providing and Construction of CTB with approved material complete as per MORTH Technical Specification Clause No. 406 (WMM)30,945Cum
Providing and Construction of CTB with approved material complete as per MORTH Technical Specification Clause No. 406 (WMM)9,440Cum
PAVING COURSES
Providing and laying Prime coat over granular surface as per drawing and technical specifications.1,45,000SQM
Providing and applying bituminous Tack coat @ 2.0 to 3.0 kg /10 sqm over prepared bituminous surface with bituminous emulsion all complete as per Technical Specification Clause 5031,45,000SQM
Providing and laying Dense Bituminous Macadam (DBM with VG-40, grading-2) course complete as per MoRTH Technical Specification Clause Nos 501 & 505.8,625Cum
CULVERTS
6Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads.Cum
a) In all types of Soils by mechanical means18,865Cum
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M151,340.0Cum
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. RCC M3011,552Cum
Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 16001,305MT
Providing and Laying Reinforced cement concrete for Box / Slab culverts in Superstructure excluding cost of steel complete as per drawing and Technical Specifications Sections 1500, 1700 and 2300.
a)RCC Grade M 304,284Cum
BRIDGES
7Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads.Cum
a)In all types of Soils by mechanical means34,659Cum
a)Providing and laying Cement Concrete in foundation including centring and shuttering etc. as per Drawings and Technical Specifications Section 1500,1700 and 2100 (Excluding cost of steel)1,840Cum
Providing and laying Cement Concrete in foundation including centring and shuttering etc. as per Drawings and Technical Specifications Section 1500,1700 and 2100 (Excluding cost of steel)
a) M307,516cum
b) M353,286cum
Providing and laying Cement Concrete in sub-structure including centring and shuttering etc. as per Drawings and Technical Specifications Section 1500,1700 and 2200 (Excluding cost of steel)
b) RCC M302.087cum
c) RCC M352,166cum
Providing and laying Reinforced Cement Concrete in Super structure complete as per Drawings and Technical Specifications Section 1700 & 2300.(Excluding cost of steel).
a) RCC M30864cum
b) RCC M353,078cum
d) RCC M40620cum
d) RCC M451,480cum
Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 16001,830MT
Underpasses
8Earthwork in excavation of foundation for structures complete as per drawing and Technical Specification Clause 304 with all lifts and leads.
a) In all types of Soils by mechanical means21,733Cum
Providing and laying Cement concrete for foundations excluding cost of steel complete as per drawing and Technical Specifications Section 1500,1700, 2100. PCC M151,104Cum
b)Providing and laying Cement Concrete in foundation including centring and shuttering etc. as per Drawings and Technical Specifications Section 1500,1700 and 2100 (Excluding cost of steel)
a)RCC M302,345cum
b)RCC M351,469cum
Providing and laying Cement Concrete in sub-structure including centring and shuttering etc. as per Drawings and Technical Specifications Section 1500,1700 and 2200 (Excluding cost of steel)
b) RCC M301,402cum
c) RCC M351,703cum
Providing and laying Reinforced Cement Concrete in Super structure complete as per Drawings and Technical Specifications Section 1700 & 2300.(Excluding cost of steel).
a) RCC M30821cum
b) RCC M35986cum
b) RCC M40223cum
d) RCC M45, Cast in situ1,309cum
Providing, cutting, bending and fixing in position of HYSD bar reinforcement in reinforced concrete structures complete as per drawing and Technical Specifications Section 16001,119MT
Other Work
10Providing and construction of Toe wall complete as per the drawings and Technical Specifications 1500, 1600,1700, 2100 & 2200 as directed by the Engineer.
a) Excavation in all types of soil38,700Cum
b) PCC M 15 using batching plant1,350Cum
c) RCC Grade M 30 for foundation9,478Cum
e) Reinforcement845MT
11Re Panel Erection3,439SQM
12RE wall Panel Casting15,086SQM
13Boundry wall Panel Erection1,860RMT
14Road side drains (Shoulder drain,Linne drain,Unline Drain)6,311RMT

Back to Package 3

Building the Nation, Beaming with pride

Registered Office

Amar Business Zone, C-Wing, Level 13, Baner,
Pune 411045, India

Building the Nation, Beaming with pride

Registered Office

Amar Business Zone, C-Wing, Level 13, Baner,
Pune 411045, India

© 2026 Rajpath Infracon Pvt. Ltd. All rights reserved.

CRISIL A-/Stable · Guinness World Record Holders

Building the Nation, Beaming with pride

Registered Office

Amar Business Zone, C-Wing, Level 13, Baner,
Pune 411045, India

Building the Nation, Beaming with pride

Registered Office

Amar Business Zone, C-Wing, Level 13, Baner,
Pune 411045, India

© 2026 Rajpath Infracon Pvt. Ltd. All rights reserved.

CRISIL A-/Stable · Guinness World Record Holders