| Date | Milestone | Days from appointed date | Planned progress |
|---|---|---|---|
| 29-8-2024 | Project Milestone 1 | 200 | 20% |
| 20-3-2025 | Project Milestone 2 | 450 | 35% |
| 18-9-2025 | Project Milestone 3 | 600 | 75% |
| 1-3-2026 | Schedule Completion Date | 910 | 100% |